Creating a Task List

1 byte removed, 13:08, 20 June 2013
Effort Verses Duration
* '''Accrue Hours''' – provides for time and effort to be tracked against the task before the budget is established. This feature is used to add the cost of preparing an estimate into the project.
==Effort Verses Versus Duration==
It is important to recognize the difference between effort and duration.
* Effort is defined as the amount of work measured in hours or days required to complete a task.
* Effort can be specified at the task level, or specified when you assign a resource to a task. If you assign multiple resources, the effort will increase but not the duration.
* Duration is defined by the time elapsed between the start and the end of the task.