Level 3 Activity List Batch Update

From SmartWiki
Revision as of 08:39, 23 July 2013 by Arthur Lathrop (talk | contribs) (Configuring Activity List Batch Update)

Jump to: navigation, search

The Level 3 Activity List Batch Update feature allows the status of one or more Level 3 Activities to be changed directly from the Level 3 List View.

  • This includes both the List View of all Level 3 activities (if enabled) and the list of Level 3 activities at the bottom a Level 2 record.


The process is illustrated here:

  • Select the appropriate records and click the Approve button (Note the initial status is Submitted)
L3BatchSubmitted.png


  • Click OK to accept the change:
L3BUpdateconfirm.png


  • The result with status changed to Approved for Invoicing:
L3BatchApproved.png


Configuring Activity List Batch Update

There are two settings that must be configured to use the Level 3 Activity List Batch Update


1) Manager Permission:
The Roles permitted to use this feature must be selected for each UTA via the Manager Permission setting under Roles & Permissions:

L3BatchUpdateMgrPerm.png


2) UTA Settings:
The destination Status must be set on the Application Configuration page, found within the Level 3 Settings section:

L3BatchUpdateSettings.png

The label for the button can also be defined in this section.

Note: if no label is entered the default label of Approve will be used.

Notes

  • If the Batch Update Level 3 to: Status setting on the Application Configuration page is set to --Disabled-- the button will not appear.
  • Only one Status can be set in this manner.
  • Any Level 3 record displayed can be changed with this feature. Users must be careful to not change the status of any records that should not be changed (i.e.: from Invoiced to Approved for Invoicing)

See Also