Level 3 Activity List Batch Update
From SmartWiki
The Level 3 Activity List Batch Update feature allows you to change the status of one or more Level 3 Activities from the Level 3 List View below a Level 2 record.
The process is illustrated here:
- Select the appropriate records and click the Approve button (Note the initial status is Submitted)
- Click OK to accept the change:
- The result with status changed to Approved for Invoicing:
Configuring Activity List Batch Update
There are 2 settings that must be configured to use the Activity List Batch Update:
- The Roles permitted to use this feature must be selected for each UTA via the Manager Permission page.
- The destination Status must be set on the Application Configuration page.